Current Projects

Fire Station # 2
Location - 206 S. Parks Dr.
• Architect: Architect Design Group, Inc. (ADG)
• Contractor: JC Commercial, Inc.
• Project: A new Fire Station With Fire Administration offices will be constructed in the vicinity of Parks Dr. and Belt Line Rd. Upon completion of the new Fire Station, the existing Fire Station at Hampton Rd. and First St., will be removed.
• Project Status: Construction started (7/18)
                             Construction 5% complete, waterline being installed (8/18)
                             Utilities complete, Drilling piers (9/18)

                             Utilities complete, Drilling piers (10/18)
                             Utilities complete, Drilling piers (11/18)
                             Utilities complete, Drilling piers, project 20% complete (12/18) 
• Projected completion Fall 2019 

2016 Water/Wastewater Renovation & Replacement Project - Phase 2

 
Various Locations
• Engineer: Dick Perkins, P.E.
Contractor: Raytech Services, LLC
Project: The 2016 R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water lines. In most cases the infrastructure is 40-50 years old. Project location is from, N. Westmoreland Rd. Water Line (St.
Anne Episcopal Church North to Cedar Rapids Ln. ). Phase II will consist of Street Reconstruction of both Deborah and David Avenues. 
Project Status: Construction 90% complete (Milling complete, Finishing concrete work) (7/18)
                             Construction 90% complete (Milling complete, Finishing concrete work) (8/18)
                             Construction 95% complete (Milling complete, Finishing concrete work) (9/18)

                             Construction 99% complete (Milling complete, Finishing concrete work) (10/18)
                             Construction 99% complete (Issued Final Punchlist) (11/18)
                             Construction complete (awaiting record drawings) (12/18)
Projected Completion Summer 2018

2018 Water/Wastewater Renovation & Replacement Project - Phase 1

Hunters Creek Dr., Foxwood Dr., Prairie Creek Dr. and Shadywood Lane
• Engineer: Dick Perkins, P.E.
Contractor: TBD
Project: Included in the Capital improvement Program (CIP) is the annual expenditure of R & R
(Renovation and Replacement) funds which are used to upgrade deteriorating water and wastewater infrastructure. The current R & R Project includes various locations with varying degrees of deterioration of the existing clay tile sewer lines and cast iron water
lines. In most cases the infrastructure is 40-50 years old. The water and sewer main lines will be replaced with Polyvinyl Chloride (PVC) pipe. In addition, water service lines will be replaced (City side of the meters) and sewer lines will be replaced up to the
property lines with cleanouts being installed at the property line. In accordance with the CIP, the following streets have water, sewer and paving infrastructure that will be replaced:

Project Status: 
 Design (7/18)
                             Design Complete (8/18)
 
                            Advertise/Bid for Construction (9/18)
                             Project Awarded to Contractor (10/18)
                             Pipe bursting sanitary sewer lines on Hunters Creek (11/18)
                             Pipe bursting sanitary sewer lines on Hunters Creek 40% complete, pavement to start in January 2019 (12/18)
• Construction anticipated to begin Fall 2018