Subdivisions

Kentsdale Farm Phase III
67 lots – Residential
Project Status: 
Construction 50% Complete: All Utilities Installed, paving remaining (5/17)
                           Construction 50% Complete: All Utilities Installed, paving remaining (6/17)
                           Construction 75% Complete: All Utilities Installed, paving remaining (7/17)
                           Construction 90% Complete: Paving remaining (8/17)
                           Construction 95% Complete: Final Grade and Blockouts (9/17)
                           Construction 99% Complete: Final Grade and Blockouts (10/17)
                           Construction 99% Complete: Final Grade and Blockouts (11/17)
Developer: Bloomfield Homes
Engineer: Engineering Concepts & Design, L.P.
Contractor: Conatser Construction 
  
Silver Creek Meadows Phase II
80 lots – Residential
Project Status: 
Construction 99% Complete, Box Culvert and Paving remaining, Water Line Relocated on May 22, 2017 (5/17)
                           Construction 99% Complete, Paving over culvert box and connecting to streets remaining (6/17)
                           Construction 99% Complete: Paving over culvert box and connecting to streets remaining (7/17)
                           Construction 99% Complete: Paving over culvert box and connecting to streets remaining (8/17)
                           Construction 99% Complete: Paving over culvert box and connecting to streets remaining (9/17)
                           Construction 99.5% Complete (10/17)
                           Construction Substantially Complete (11/17)
Developer: Skorburg Company

Engineer: Bannister Engineering
Contractor: Lacy Construction
   
Elerson Trace Park  
30 lots – Residential
Project Status: 
Design Review (5/17)
                           Design Review (6/17)
                           Design Review Complete (7/17)
                           Design Review Complete - Awaiting Planning and Zoning Release for Pre-Con Meeting (8/17)
                           Design Review Complete - Awaiting Planning and Zoning Release, Grading started awaiting Pre-Con Meeting (9/17)
                           Site Grading Commenced (10/17)
                           Construction 5% Complete, installing sewer (11/17) 
Developer: Wildwood Development Company I, L.P. 

Engineer: Crannell, Crannel & Martin
Contractor: Wildwood Development Company I, L.P.

The Homestead at Daniel Farm - Phase 1A 
68 lots – Residential
Project Status: Design Review (6/17)
                           Design Review (7/17)
                           Design Review (8/17)
                           Design Review (9/17)
                           Design Review (10/17)
                           Design Review (11/17)
Developer: Wildwood Development Company I, L.P.

Engineer: Dietz Engineering
Contractor: TBD

Summit Parks Phase 2 
72 lots – Residential
Project Status: Design Review (11/17)
Developer: Alluvium Development

Engineer: Bannister Engineering
Contractor: TBD