commercial projects

Comfort Suites Hotel
• Location: Wintergreen Rd. West of I-35
• Project Status: 
On Hold Pending Pre-Construction Meeting (8/17)
                             On Hold Pending Pre-Construction Meeting (9/17)
                             On Hold Pending Pre-Construction Meeting (10/17)
                             Pre-Construction Meeting Scheduled (11/17)
                             Pre-Construction Meeting Scheduled (12/17)
                             Site Grading work under-way (1/18)
• Projected Completion Fall 2018

  
The Village UMC

• Location: Wintergreen Rd. West of I-35
• Project Status: 
On Hold Pending Pre-Construction Meeting (8/17)
                             On Hold Pending Pre-Construction Meeting (9/17)
                             On Hold Pending Pre-Construction Meeting (10/17)
                             On Hold Pending Pre-Construction Meeting (11/17)
                             On Hold Pending Pre-Construction Meeting (12/17)
                             Awaiting pending Pre-Construction Meeting (1/18)
• Projected Completion Pending  
  
Home 2 Suites Hotel
• Location: Centre Park Blvd. – west of I-35 frontage Rd.
Project Status: FINAL Pending (8/17)
                             FINAL Pending (9/17)
                             FINAL Pending (10/17)
                             FINAL Pending (11/17)
                             FINAL Pending (12/17)
                             FINAL Pending Punch-list (1/18)
• Structure Status: 95% Complete (8/17)
                                 95% Complete (9/17)
                                 97% Complete (10/17)
                                 98% Complete (11/17)
                                 99% Complete (12/17)
                                 99% Complete (1/18)
• Projected Completion Spring 2018
     
 
Best Western - GLO Hotel
• Location: I-35 Frontage Rd. between The Meadows Pkwy and Southpointe Dr.
• Project Status: Civil Infrastructure 65% Complete (8/17)
                             Civil Infrastructure 85% Complete (9/17)
                             Civil Infrastructure 95% Complete (10/17) 
                             Civil Infrastructure 95% Complete (11/17)
                             Civil Infrastructure 99% Complete (12/17)
                             Civil Infrastructure 99% Complete (working on interior) (1/18) 
• Structure Status: 10% Complete (10/17)
                                 30% Complete (11/17)
                                 60% Complete (12/17)
 
                                75% Complete (1/18) 

• Projected Completion Spring 2018

PROLOGIS Building 1
• Location: South-east corner of Danieldale Rd. and Polk St.
• Project Status: Civil Infrastructure 70% Complete, Storm Sewer and Sanitary Sewer (8/17)
                             Civil Infrastructure 90% Needs Paving (9/17)
                             Civil Infrastructure 90% Needs Paving (10/17)
                             Civil Infrastructure 95%, Paving 50% (11/17)
                             Civil Infrastructure 95% Complete (12/17)
                             Civil Infrastructure 99% Complete (1/18) 
• Structure Status: 15% Complete (11/17)
                                 25% Complete (12/17) 
                                 95% Complete (1/18)  

• Projected Completion Spring 2018

 
Hillwood Crossroads Trade Center Building 3
• Location: I-35 Frontage Rd. between Danieldale Rd. and Wintergreen Rd.
• Project Status: Civil Infrastructure 90% Complete, Water and Storm Drainage complete (8/17)
                             Civil Infrastructure 99% Needs Paving (9/17)
                             Civil Infrastructure 99.5% Needs Remaining Paving (10/17)
                             Civil Infrastructure Complete, Paving 99% Complete (11/17)
                             Civil Infrastructure Complete, Paving  Complete, Awaiting Final (12/17)
                             Civil Infrastructure Complete (1/18)
• Structure Status: 10% Complete (10/17)
                                 30% Complete (11/17)
                                 75% Complete (12/17)
                                 100% Complete (1/18) 
• Projected Completion Winter 2018
  
Elementary School Offsite Roadway
• Location: Parkerville Rd. east of Meadow Creek Park
• Project Status: 
Site Prep and Paving 85% Complete, Grading Complete  (8/17)
                             Site Prep and Paving 90% Complete, Grading Complete  (9/17)
                             Paving 95% Complete (10/17)
                             Paving Complete (11/17)
                             Paving Complete, Awaiting Final (12/17)
                             Paving Complete, Awaiting Final (1/18)
• Structure Status: N/A
• Projected Completion Winter 2018
  
Desoto House of Peace Community Center
• Location: Belt Line in front of Summit Parks
• Project Status: 
Design Review (8/17)
                             Design Review (9/17)
                             Design Review Complete (10/17)
                             Awaiting Pre-Construction Meeting (11/17)
                             Awaiting Pre-Construction Meeting (12/17)
                             Awaiting Pre-Construction Meeting (1/18)
• Structure Status: TBD
• Projected Completion TBD
  
Katherine Johnson Technology Magnet
• Location: Parkerville Rd. east of Meadow Creek Park
• Project Status: 
Civil Infrastructure, Storm Sewer and Sanitary Sewer (8/17)
                             Civil Infrastructure, Storm Sewer and Sanitary Sewer and Framing (9/17)
                             Civil Infrastructure 95% Complete, Storm Sewer and Sanitary Sewer and Framing (10/17)
                             Civil Infrastructure, Storm Sewer and Sanitary Sewer 99% Complete, Framing 50% Complete (11/17)
                             Civil Infrastructure, Storm Sewer and Sanitary Sewer Complete, Framing 75% Complete (12/17)
                             Civil Infrastructure, Storm Sewer and Sanitary Sewer Complete, Framing 95% Complete (1/18)
• Structure Status: 10% Complete (9/17)
                                 20% Complete (10/17)
                                 45% Complete (11/17)
                                 70% Complete (12/17)
                                 90% Complete (12/17)
• Projected Completion Spring 2018
 
Grocery Store - Lot 1, Block A 
• Location: North-West corner of belt Line Rd. and Westmoreland Rd.
• Project Status: 
Design Review (8/17)
                             Design Review (9/17)
                             Design Review Complete (10/17)
                             Awaiting Pre-Construction Meeting (11/17)
                             Awaiting Pre-Construction Meeting (12/17)
                             Awaiting Pre-Construction Meeting (1/18)
• Structure Status: TBD
• Projected Completion TBD

DeSoto Nursing and Rehabilitation Center 
• Location: South-West corner of Hampton Rd. and Centre Park Blvd.
• Project Status: 
Design Review (8/17)
                             Design Review (9/17)
                             Design Review (10/17)
                             Design Review (11/17)
                             Design Review Complete (12/17)
                             Awaiting Pre-Construction Meeting (1/18)
• Structure Status: TBD
• Projected Completion TBD

Athlos - Desoto K-8 Charter School 
• Location: South-East corner of Cockrell Hill Rd. and Wintergreen Rd.
• Project Status: 
Design Review (8/17)
                             Design Review (9/17)
                             Design Review (10/17)
                             Design Review (11/17)
                             Design Review of Traffic plan (12/17)
                             Design Review of Traffic plan (1/18)
• Structure Status: TBD
• Projected Completion TBD

Love Storage
• Location: South-East corner of Hampton Rd. and Danieldale Rd.
• Project Status:
Design Review (9/17)
                             Design Review (10/17)
                             Design Review (11/17)
                             Design Review (12/17)
                             Design Review (1/18)
• Structure Status: TBD
• Projected Completion TBD

La Quinta Inn & Suites
• Location: I-35 Frontage Rd. and Centre Park Blvd.
• Project Status:
Design Review (12/17)
                             Design Review (1/18)
• Structure Status: TBD
• Projected Completion TBD